Most London kitchen renovations take between three and six weeks on site, but the honest answer is that the building work is rarely the slowest part. Lead times on units, a rewire you did not budget for, and a flat that needs freeholder consent can all add weeks before anyone lifts a hammer. Here is what actually happens, and when.
For a straightforward kitchen swap in the same footprint, plan for around two to three weeks on site. Move the sink, change the layout, or knock through into a dining room and you are looking at four to six weeks. Add a rear extension and the kitchen fit is simply the last month of a much longer programme.
These are working weeks, not calendar weeks. Bank holidays, a plasterer who is finishing another job, and the two or three days that plaster needs to dry properly all stretch the calendar.
If you are having stone, quartz or a solid surface worktop, it cannot be measured until the units are physically installed and level. The templater then takes the job away and the worktop is cut off site. That gap is usually 7 to 14 working days, and in that period you have units with no tops, no sink and no hob.
Laminate worktops can be cut on site the same day, which is why a budget kitchen often finishes a fortnight sooner than a premium one. If you want stone and a short timeline, book the templater provisionally the moment the units are ordered.
Planning your start date around the paperwork matters more here than almost anywhere else. In a flat, most leases require written consent from the freeholder or managing agent before you start, particularly for anything touching plumbing or hard flooring. That correspondence can easily take four to six weeks, so send it early.
Access is the other London tax. In a terrace in Hackney or a Victorian conversion in Wandsworth, everything comes in and out through the front door and up a staircase. Councils across Greater London require a permit for a skip on the public highway, typically a few days to arrange, and some boroughs restrict skips on red routes altogether, meaning waste has to be bagged and carried.
Older London housing stock hides surprises. Lift the floor in a 1900s terrace and you may find rotten joists, a redundant chimney breast, or an under-sink waste that runs the wrong way. Electrics are the most common one: if the consumer unit will not take the extra circuits a modern kitchen needs, that is a day or two of extra work and a new certificate.
Client-side changes are the other big one. Deciding to move the hob after first fix means the electrician comes back, and the tiler gets pushed a week. Lock the layout and every appliance model before the strip out begins, because appliance dimensions drive the cabinetry.
Order the kitchen before the start date, not after. Standard ranges from the big suppliers usually arrive in 2 to 4 weeks, bespoke joinery in 8 to 12 weeks, and appliances have been the single least predictable item in recent years.
Have everything on site before the strip out: tiles, taps, handles, flooring, sink, lighting. A job stops dead waiting for a single item, and a stopped job loses its place in the trades' diaries. It is also worth setting up a temporary kitchen somewhere else in the house, a kettle, microwave and a fridge, because you will be without a working one for most of the programme.
Yes, most people do, though you will have no cooking facilities or kitchen sink for two to four weeks and there will be dust and noise during weekday working hours. Set up a temporary kitchen elsewhere and plan to wash up in the bathroom.
The timeline is driven by the number of stages, not the square metreage. A small galley kitchen still needs first fix, plastering, drying time, worktop templating and second fix, and each of those has a minimum duration regardless of size.
For a good builder in London, expect roughly four to eight weeks from agreeing a quote to starting on site, and longer if you need freeholder consent or bespoke joinery. Use that lead time to finalise the design and get materials ordered.